How a Korean Soju Brand Got 200,000 Custom Bottles in 18 Days for New Year Launch

Oct.29.2026

Case Study · Peak-Season Production

How a Korean Soju Brand Got 200,000 Custom Bottles in 18 Days for New Year Launch

When the original supplier failed with 20 days to go, transparent scheduling, in-house inspection and tiered pricing delivered 200,000 custom glass bottles — two days ahead of the New Year deadline.

200,000 custom 750ml soju bottles delivered in 18 days for a Korean New Year launch
From a failed supplier with 20 days to go — 200,000 custom soju bottles delivered in-house, two days before the New Year deadline.

A Korean soju brand's design studio discovered just 20 days before the New Year launch that their original supplier could not deliver 750ml custom soju bottles on time. By providing tiered pricing for fast order confirmation, a transparent production schedule, and 100% in-house inspection, we produced and delivered 200,000 custom glass bottles to the Korean filling plant within 18 days — 2 days ahead of the client's deadline. The client subsequently added us as their preferred supplier with a full-year supply contract.

1. Executive Summary

18
Days from order to delivery
200k
Custom bottles delivered
<0.5%
Breakage rate on filling line
100%
Manual full inspection before shipment

For a seasonal spirits release, missing the launch window means losing an entire year of sales. This case study breaks down exactly how we compressed production, inspection and ocean shipping into an 18-day window — including the 48-hour production schedule that gave the client confidence to commit.

Why this case matters

Peak-season launches are the hardest test of a supplier's real capacity. The client had been burned before by high breakage rates from Chinese factories. This time, the combination of a visual production schedule and a dual-track inspection system changed the outcome — and the relationship.

2. Client Background

The client is the founder of a well-known design studio based in Seoul, Korea, acting on behalf of their brand client. The end client is a mid-to-premium soju brand in Korea, with products sold through convenience stores, restaurants, and gift channels. The project was directly tied to the brand's image, production schedule, and New Year product launch — there was zero margin for error.

The client contacted us through a B2B platform with an initial requirement of 200,000 units of 750ml custom soju bottles. The specification called for high-white glass, a classic soju bottle silhouette, but with a customized shoulder curve and a proprietary embossed design on the bottle base.

Seoul design studio and Korean premium soju brand display — convenience store and gift channel context
A Seoul-based design studio acting for a mid-to-premium soju brand sold through convenience stores, restaurants and gift channels.

3. The Challenge

After sample approval and just before the order was to be placed, the client raised two urgent concerns:

  • Extremely tight lead time: The client required all bottles to arrive at the Korean filling plant within 20 days to meet the New Year launch window. Standard soju bottle production and ocean shipping typically take 35–45 days.
  • Serious quality concerns: The client admitted that past purchases of glass spirits bottles from China had suffered from high breakage rates — bottles could not withstand the pressure of automated filling lines, causing frequent line stoppages and yield losses. The client stated clearly that if the same problem occurred again, they would permanently abandon Chinese suppliers.

In addition, producing 200,000 units in 18 days is an extreme capacity scheduling challenge for any glass bottle factory.

Previous supplier · filling line breakage rate 5–8%
This project · filling line breakage rate <0.5%

The client's concern was not unreasonable — a bottle that cannot survive the filling line is a liability, not a saving. What they needed was evidence, not promises.

Glass soju bottle filling line breakage and machine pressure test — quality control challenge
Past suppliers gave 5–8% breakage on the filling line. This project needed to prove a <0.5% rate before the client would commit.

4. The Solution

We did not offer vague promises. Instead, we responded to the client's two core concerns with data-driven and visual proof.

01
Visual Production Scheduling

Within 48 hours of confirming requirements, we provided a detailed production and logistics schedule breaking down the entire process — mould confirmation, raw material preparation, production, quality inspection and ocean shipping — each with precise time allocations. This proved the 18-day accelerated plan was feasible.

02
Dual-Track Inspection + Third-Party Verification

100% manual full inspection on every bottle (mouth, body, base), plus automated machine pressure testing simulating filling-line conditions. SGS third-party reports from previous production runs objectively verified pressure resistance and low defect rate.

03
Tiered Pricing for Fast Decision

Tiered pricing for 5,000 / 10,000 / 20,000 cases at the quotation stage, allowing the client to evaluate cost and scalability against budget and market size. Combined with sample video confirmation, the client locked in the order quickly.

Day 1–3
Mould Confirmation & Raw Material Preparation

Confirmed the mould matched the client's specification for the 750ml high-white glass soju bottle, including the customised shoulder curve and proprietary embossed base design. Raw material procurement began in parallel to compress the schedule.

Day 4–13
Emergency Production · 200,000 Units

Full-scale emergency production of 200,000 units, with 100% manual inspection (mouth, body, base) and machine pressure testing applied to every batch. Daily output optimised to meet the compressed schedule without compromising the inspection protocol.

Day 14–18
Efficient Logistics · Arrival at Korean Filling Plant

Logistics arranged in coordination with production completion. Goods arrived at the Korean filling plant within 8 days of shipment, ahead of the client's 20-day deadline and in time for the New Year launch.

Project Parameters ───────────────────────────── Bottle 750ml high-white glass soju bottle Custom features Custom shoulder curve + embossed base design Quantity 200,000 units Production 18 days total (production → delivery) Inspection 100% manual + machine pressure test Third-party SGS pressure resistance + defect reports Logistics Ocean shipping, 8 days to Korean filling plant
Custom soju bottle mold confirmation — engineer reviewing technical drawings in factory workshop
Fig 1. Day 1–3: Mould confirmation and raw material preparation — matching the client's custom shoulder curve and proprietary embossed base design.
100% manual inspection and machine pressure testing on every custom soju bottle
Fig 2. Day 4–13: Every bottle undergoes 100% manual visual inspection (mouth, body, base) plus machine pressure testing that simulates filling-line conditions.
200,000 custom soju bottles on pallets ready for container loading — 18-day logistics execution
Fig 3. Day 14–18: Logistics arranged in coordination with production. Goods arrived at the Korean filling plant within 8 days of shipment, 2 days ahead of deadline.

5. The Results

Project Outcome Summary
Metric Target Achieved
Lead time (production to delivery) 20 days 18 days ✓
Filling line breakage rate — <0.5% ✓
Filling line stoppages None None ✓
Manual inspection coverage — 100% ✓
Deadline buffer 0 days +2 days ✓
  • Lead time: Production to delivery completed in 18 days. The client's New Year launch proceeded as scheduled.
  • Breakage rate: The client's filling line reported a breakage rate below 0.5%, far better than the previous supplier's 5%–8%. The filling line experienced no stoppages due to bottle quality issues.
  • Client feedback: After receiving the goods, the client proactively sent this message: "NEWRAY proved its professionalism through action. They are not just a supplier, but a truly reliable solutions partner."
  • Long-term partnership: The client named us their preferred supplier and added multiple full-year supply contracts covering regular products and holiday special editions.
Finished 750ml custom soju bottle — high-white glass with custom shoulder curve and embossed base, New Year gift edition
Fig 4. The finished 750ml high-white glass soju bottle — custom shoulder curve, proprietary embossed base, delivered 2 days ahead of the New Year launch.

6. Client Testimonial

"Past suppliers from China gave us high breakage rates on the filling line. This time, not a single issue. The bottles ran clean from start to finish." — Founder, Korean Design Studio

7. Call to Action

Is your peak-season launch being held hostage by supplier delays? Send us your bottle type and quantity requirements. We will provide a visual production schedule and tiered pricing within 48 hours — so you can see the entire timeline before you commit.

Whether you need a custom soju bottle, a glass spirits bottle, or a private label liquor bottle with urgent delivery, we handle production, inspection, and logistics with full transparency. One partner, one timeline, one point of accountability.

48-Hour Production Schedule

Send Us Your Bottle Type and Quantity Requirements

Share your bottle specification and delivery deadline. We will come back with a visual production schedule and tiered pricing — so you can see the entire timeline before you commit. No obligation, no vague promises.

Get a Quote

Our representative will contact you soon.
Email
Mobile/WhatsApp
Name
Company Name
Message
0/1000

Get a Quote

Our representative will contact you soon.
Email
Mobile/WhatsApp
Name
Company Name
Message
0/1000